We’ve replaced an ageing watermain in Archies Creek to improve water supply and reduce interruptions for customers in the surrounding area.

The Archies Creek water main renewal is one project under a $1.6M program of watermain renewals across the network.

This project was completed in November 2023.

About the works

A 750m section of watermain was replaced via directional boring, which is a low-impact method of installing underground pipes.

Directional boring, also known as directional drilling, is a trenchless technology that enables us to install a watermain with minimal disruption to the environment. It involves minimal surface excavation and enables the project to be completed with less impact on existing infrastructure, road users and residents.

Once installed, the new pipes were cleaned, pressure tested, disinfected and flushed ready to supply customers.

Impact on water services

There was one planned shutdown for the watermain to be connected to the network. This occurred on a weekday between the hours of 9am – 5pm. Affected customers will be notified via letter five business days prior.

No other water interruptions occurred during the works.

Budget

$0.35 M

Location

Near Archies Creek Rd, Dalyston.

Timeframe

Early September 2023 to late November 2023.

Contact us

If you would like more information about this project, please contact Project Manager Harsha Puvvala at westport@westernportwater.com.au or call 1300 720 711.