Project overview
- Westernport Water has three pipelines connected to the underside of the San Remo / Phillip Island Bridge.
- These pipes provide vital water and wastewater services to Phillip Island and San Remo, transporting approximately 802.15 ML of drinking water and 503 ML of sewage to the Island annually.
- The brackets, fixtures and fittings connecting these pipelines to the bridge require proactive maintenance work to extend the life of the pipelines for another 30 years.
- Scaffolding is suspended under the bridge so workers can safely access the pipes while minimising impacts to traffic and pedestrians.
- The $5.5M San Remo Bridge Pipeline Bracket Renewal Project is being delivered by Westernport Water, with Freyssinet Australia the principal contractor.
- Works will take place between 26 February 2024 and December 2024.
- Occasional partial lane closures will be required while navigational markers for marine users are relocated. This will occur during the day in off-peak times.
Project Timeline
Stay informed about what stage we are up to of the San Remo / Phillip Island Bridge Pipeline Bracket Renewal project… Read more
Contact us
- A dedicated project mailbox has been setup by Westernport Water for this project please email bridgeproject@westernportwater.com.au.
- Alternatively, contact our Customer Service Team on 1300 720 711