On this page you will find information on all water and sewerage works that have been completed over the past week in the Westernport Water service area.

Completed Last 7 Days

Planned shutdown of water supply

03 May 2024

Abingdon Link and Pembrey Loop, Cowes

Abingdon Link and Pembrey Loop, Cowes

There is a planned shutdown today for a watermains cut-in, affecting 5 properties along Abingdon Link and Pembrey Loop, Cowes.

Both potable and recycled water will be isolated between 9am and 1pm.

 

 

 

 

 

Civil works - changes to traffic conditions

15 Apr 2024

Bass Hwy, Dalyston Glen Forbes Road, and Walker Street

Westernport Water is undertaking civil works to improve access for Westernport Water staff and contractors at the Dalyston Pump Station.

When: Monday 15 April 2024 until approximately 10 May 2024.

Work hours: 7:00am to 5:00pm, Monday to Friday (excluding public holidays).

Contractor: SR Excavations.

Impacts: Residents nearby may experience noise, vibrations, and temporary disruptions due to the work.

The speed limit on Bass Hwy, Dalyston Glen Forbes Road, and Walker Street will be reduced to 40km per hour.

Occasional westbound lane closures on Bass Hwy are expected to occur for approximately four days over the course of three weeks.

We understand that these works may cause inconvenience, and we appreciate your patience and cooperation during this time.